Hofats Shopify Build

Roadmap & Next Steps

The rough plan

Estimates are per-task, not per-day, since some bits take half a day and others take longer depending on how the integrations behave. View live preview → (password sent separately in the email)

1Storefront structure complete

~5–6.5 days

The core site skeleton takes shape — navigation, homepage, and reusable category/product templates all live, so later content just slots straight in.

2Content complete

~3–3.5 days

The real content goes in — blog posts, the brand story, and the dealer locator.

3Store fully functional

~3–4.5 days

The commercial backbone connects — stock syncs automatically, shipping is configured, and customers can actually complete an order start to finish.

4Marketing tools live

~1 day

Post-purchase tools switch on — automated email marketing and review collection.

5Launch

~2–2.5 days

Domain goes live, you're trained on running things day-to-day, and the store officially launches.

Total estimate~16–18 days